Construction
Three phases · 2026–2029
Works are underway. Pile drilling finished on 7 August 2026. Foundations are planned for September.
Timeline
01
Phase 1 · 47 apartments
Start June 2026. Ready Q1 2027 through July 2027.
02
Phase 2 · 94 apartments
Planned readiness in 2028.
03
Phase 3 · 86 apartments
Planned readiness in 2029.
Building permit BIS-BL-719119-104641. Construction underway.

Site diary
Short notes on what is already done. Factual in tone, without excess promise.

06.2026
Site setup
Preparing the plot, access roads, and the working area ahead of pile works.
20.07.2026
Site prepared
The site was accepted for the next stage. Pile testing followed in July.
07.08.2026
Pile drilling finished
The pile field for the phase 1 buildings is complete.
09.2026
Foundations
Foundation structures are planned to finish in September.